The Ohio Turnpike is performing bridge rehabilitation work on eight bridges throughout Fulton County affecting County and Township roads over the turnpike. The tentative bridge/road closure dates are as follows:
Bridge/Road Closure Date Open Date Duration
TR 26-2 5/6/14 5/19/14 14 Days
TR 16 5/12/14 5/26/14 14 Days
CR 21 5/19/14 6/1/14 14 Days
CR 20 6/2/14 6/23/14 21 Days
CR 19 6/23/14 7/1/14 7 Days
CR 17-3 8/4/14 8/11/14 7 Days
TR 17 8/11/14 8/25/14 14 Days
CR 23 10/6/14 10/27/14 21 Days
Please contact the Fulton County Engineer’s Office for updated closure dates. Detours are posted.